A team has started a new agile project and the project manager wants to establish a feedback loop to ensure continuous learning and improvement. What should they do to accomplish this goal?
a.
Request weekly status reports.
b.
Have a monthly conference call with the stakeholders.
c.
Implement a sprint review at the end of each sprint.
d.
Only communicate with team members via email.
e.
Monitor team progress by watching their screen constantly.
f.
Hold daily 4-hour meetings to discuss progress.