Agile Project Management - Agile Change Management - Scrum framework
Beginner
1/5
A Scrum Team is experiencing issues with excessive meetings. The Product Owner has already included all the essential meetings in their schedule. What should the Scrum Master do?
a.
Add more meetings to improve communication.
b.
Leave the team to handle the meetings.
c.
Ask team members to handle meetings independently.
d.
Review and optimize the existing meetings.
e.
Ignore the problem and follow the schedule.
f.
Cancel all non-essential meetings.
Beginner