During a project retrospective, the team identified that the project scope has grown significantly. The team believes this is due to stakeholders making changes without going through a formal process. What should the project manager do?
a.
Ignore the issue and proceed
b.
Change project objectives
c.
Remove stakeholder input
d.
Increase project budget
e.
Implement a change control process to handle scope changes
f.
Decrease project duration