Agile Project Management - Agile Release Planning - Release Plan
Master
1/5
The team has been allocated a budget of $100,000 for a project. The Product Owner has identified three features, each having an equal business value, but different costs: Feature A ($40,000), Feature B ($30,000), and Feature C ($50,000). Which feature should the team work on first?
a.
Feature B
b.
Work on all features simultaneously
c.
Randomly choose a feature
d.
Feature A
e.
Feature C
f.
Ask for an increased budget
Master