Agile Project Management - Agile Roles and Responsibilities - Scrum Master
Beginner
1/5
During a Sprint Review, the stakeholders are unhappy with a recently completed feature. What should the Scrum Master do?
a.
Change the project deadline to accommodate the stakeholders' requests.
b.
Encourage open communication between the stakeholders and the development team to understand the issue and adapt the Product Backlog accordingly.
c.
Blame the development team for not understanding the requirements.
d.
Ask the stakeholders to communicate their concerns after the Sprint Review.
e.
Ask the Product Owner to prioritize fixing the feature above all other work.
f.
Ignore the stakeholders' concerns and proceed with the next Sprint.