During an Agile project, the customer requests to be informed of the most likely and worst-case scenarios for the project completion date. What forecasting technique should you use?
a.
Ignoring forecasting and providing the customer with the maximum possible completion date
b.
Using deterministic forecasting with a fixed date based on average team velocity
c.
Using expert opinion to derive most likely and worst-case scenarios without considering data
d.
Taking the historical data for similar projects and adding a safety margin for the worst-case scenario
e.
Assuming the team will perform consistently and provide the customer with the current project status
f.
Probabilistic forecasting with percentile confidence intervals