Register
8:59
Stop
Agile Project Management - Lean Software Development - Eliminate Waste
Beginner
1/9
While planning the iteration, the team realizes they lack the expertise to complete a critical task. What should they do?
a.
Assign the task to a team member regardless of expertise
b.
Attempt the task without seeking help and hope for the best
c.
Remove the task from the project scope
d.
Discuss the issue with stakeholders and explore options, such as training or external resources
e.
Split the task among all team members, regardless of their knowledge
f.
Delay the entire iteration until the expertise is acquired
Beginner