During a Product Backlog refinement session, the team uses T-shirt sizing for estimation. The Product Owner believes that the team is overestimating the complexity of a specific user story. What should be done?
a.
Adjust the estimation according to the Product Owner's preference
b.
Switch to other estimation methods
c.
Ask the Product Owner to estimate the story
d.
Have the team discuss and provide their reasoning
e.
Ignore the Product Owner's concern
f.
Delay the story until further clarification