Intermediate
1/12
As a project manager, your team encounters an unexpected problem that was not mentioned in the risk management plan causing a potential delay in the project. What should be your immediate action?
a.
Estimate the delay and adjust the deadline accordingly.
b.
Deal with the problem using the change control process and update the risk management plan.
c.
Ignore the problem as it was not anticipated in the plan.
d.
Immediately inform the stakeholders about the delay.
Intermediate