CAPM - Project Life Cycle - Execution
Beginner
1/5
During project execution, Michael notices that his team is consistently missing scheduled task completions. Instead of immediately addressing the missed deadlines, the team seems to be focusing on less critical tasks. What should be Michael's first step in mitigating this situation?
a.
Re-affirm the project priorities and task criticality with the team, ensuring everyone understands the project goals and their individual responsibilities.
b.
Ignore the situation, as it may correct itself over time.
c.
Delegate the task of managing deadlines to a team member.
d.
Set up immediate punishment measures for missed deadlines.
Beginner