CAPM - Project Stakeholder Management - Stakeholder Expectation Management
Beginner
1/12
As the project manager, you find that a stakeholder's expectations are heavily based on an outdated technology preference, whereas the project is set to utilize cutting-edge technology which is crucial to the project's success. How should you manage the stakeholder's expectations?
a.
Postpone discussions about technology preferences until the project is closer to completion.
b.
Compromise by incorporating some aspects of the outdated technology the stakeholder prefers.
c.
Agree to the stakeholder's preference to prevent conflict and maintain a positive relationship.
d.
Educate the stakeholder on the benefits of the new technology and its alignment with the project goals.
Beginner