CSM - Importance of Scrum Retrospectives - Ownership and Commitment
Intermediate
1/5
The team is regularly finishing the sprint ahead of the sprint end-date. What action should the Product Owner take?
a.
Engage the team in backlog refinement and pull additional user stories into the sprint if needed.
b.
Demand that the team members take more time off.
c.
Punish the team for inadequate estimation.
d.
Expect the team to maintain the pace and do more in the next Sprint.