Upon examining a Cumulative Flow Diagram (CFD) for your Agile project, you notice that all phases ('Backlog', 'In Progress', 'Testing', 'Done') are moving parallel to each other. What can be inferred from this behaviour?
a.
The team is sluggish and not productive
b.
The project is healthy, with a smooth and stable workflow
c.
The project team is probably not managing their backlog well
d.
There could be issues within the team leading to poor performance