PgMP - Program Closure Phase - Generation of Final Reports
Expert
1/17
You are a program manager generating final reports for a large-scale technology implementation program that has recently concluded. The program involved multiple vendor partnerships, cross-functional teams, and complex technical deliverables. To ensure the final reports provide a comprehensive and accurate representation of the program's outcomes, which approach should you prioritize?
a.
Rely exclusively on quantitative KPIs to measure the program's success, neglecting qualitative stakeholder feedback.
b.
Emphasize the collaborative successes, glossing over individual project specifics and technical details.
c.
Consolidate feedback on technology functionality, sidelining broader program management and partnership dynamics.
d.
Utilize diverse data sources to outline achievements, challenges, and key learnings comprehensively.