PgMP - Program Management Performance Domains - Program Activities vs. Component Activities
Master
1/5
Which of the following is an example of a program activity, rather than a component activity, in a program management context?
a.
Designing the program's stakeholder engagement strategy and communication plan
b.
Allocating resources and budgeting across the projects within the program based on priority and strategic value
c.
Establishing governance frameworks to ensure coordinated decision-making across all program components
d.
Implementing a quality management system to oversee the deliverables of each project component and ensure they meet the program's standards