PgMP - Program Management Performance Domains - Tasks in the Initiating Phase
Master
1/15
As a Program Management Professional (PgMP) initiating a program to transform a global automotive manufacturer's production processes, which of the following tasks is most essential for defining the program's scope and securing the necessary resources?
a.
Initiate a comprehensive review of industry benchmarks and competitor strategies to establish a baseline for program performance metrics and outcomes.
b.
Implement an advanced technology assessment to determine the feasibility of integrating new manufacturing systems into existing workflows.
c.
Draft an initial program charter that includes a high-level budget estimate, preliminary objectives, and an outline of potential benefits to the organization.
d.
Conduct a stakeholder analysis to identify key influencers and decision-makers and engage them in defining the program's objectives and success criteria.