Register
5:00
Stop
PMI-ACP - Agile Principles and Mindsets - Incremental Development and Delivery
Intermediate
1/5
Your project using incremental delivery approach is nearing its deadline. The client insists on a major modification that would lead to considerably more work. How should you handle this situation?
a.
Get the team start working on it while keeping the client waiting for an official response.
b.
Discuss with the client the impacts of this modification on timeline and cost and negotiate a compromise solution.
c.
Accept the modification request without any questions and put the team in crunch time.
d.
Directly refuse the modification request as it was not in the initial scope.
Intermediate