PMI-ACP - Agile Risk Management - Risk Buffering
Advanced
1/5
Project manager, Elizabeth, while reviewing the risk log, discovers a significant risk that doesn't have a designated risk owner. While the team is already loaded with existing risks, how should Elizabeth handle this situation?
a.
Elizabeth should assign it to a team member randomly without discussing.
b.
Elizabeth should ignore the risk, hoping it won't occur.
c.
Elizabeth assigns the risk to a newbie team member who has no existing risk ownership.
d.
Elizabeth should call a meeting with the team to explain the risk and collaboratively determine who can handle this new risk without being overloaded.
Advanced