PMI-ACP - Crystal Methods - Process Tailoring
Beginner
1/5
The project team using Kanban methodology is facing an issue of overflow in their 'In Progress' column due to unexpected bottlenecks. What would be the most effective process tailoring?
a.
Eliminate the 'In Progress' column
b.
Introduce more columns
c.
Introduce Work-In-Progress limits to regulate the flow and identify bottlenecks
d.
Increase the team size