PMI-ACP - Kanban Methodology - Lead and Cycle Time
Master
1/5
Your team is presented with a new project that has numerous potential risks. During your sprint planning meeting, your team decides to use an Agile Risk Board. Which of the following steps is the most essential first step to implement the risk board?