1/23
During a Daily Scrum, a member suggests to increase the length of meeting as they are not able to discuss all the items. As a Scrum Master, what would be the best approach to handle this situation?
a.
Suggest moving discussions to another meeting.
b.
Ignore the suggestion and continue with the current meeting duration.
c.
Remind the team that the purpose of the meeting is to synchronize daily work and not to discuss solutions to problems or issues.
d.
Agree to increase the duration of the Daily Scrum.