PMI-ACP - Scrum Framework - Scrum Artifacts
Expert
1/27
You are a Scrum Master. Recently the team missed their Sprint Goal for the second time in a row. Upon investigating, you observed a pattern of non-urgent requests from stakeholders being honored mid-Sprint. That is impacting the team's focus. How should you address this issue?
a.
Ask the team to work at an increased pace to accommodate stakeholder requests.
b.
Limit stakeholder interaction with the team.
c.
Educate the stakeholders about the Scrum values and the potential ramifications of frequent changes to the team and product. Arrange a meeting with stakeholders and the Product Owner to align on the Product Backlog priorities.
d.
Continue with the current approach as stakeholder requests are crucial.
Expert