PMI-ACP - Test Driven Development (TDD) - Unit Testing
Intermediate
1/8
During the inspection, the ScrumMaster observes that the team is not able to estimate story points accurately. What should the ScrumMaster do?
a.
Organize a workshop on user story point estimation
b.
Ignore the problem and hope it automatically gets better
c.
Tell the team to work without estimating story points
d.
Take over the task of estimating the user stories
Intermediate