PMI-ACP - Value-Driven Delivery - Adaptive Forward-Looking Planning
Intermediate
1/8
During the course of the project, it becomes evident that the initial estimation was unrealistic. As a follower of Adaptive Forward-Looking Planning, what should be your next step?
a.
Make adjustments and implement them without informing the stakeholders.
b.
Proceed with the initial estimate anyway, hoping the team can catch up.
c.
Stop the project until the stakeholders adjust the expectations.
d.
Revisit the plan with your team, make appropriate adjustments, and communicate with stakeholders timely.