PMI-ACP - XP (eXtreme Programming) - Continuous Integration
Advanced
1/11
The deployment team is consistently running into roadblocks during deployment, hence delaying the project timelines. As a ScrumMaster, your course of action should be?
a.
Elevate this issue to senior management without involving the affected teams.
b.
Facilitate a meeting between the development and deployment teams to better understand the issues and develop a plan to overcome these roadblocks.
c.
Demand the deployment team speed up their work, without understanding their difficulties.
d.
Ignore the issue and hope it gets resolved on its own.
Advanced