PMI-PBA - Requirements Traceability and Monitoring - Version Control in Requirements Management
Expert
1/5
When establishing version control for requirements artifacts, what is the recommended approach for managing cross-referenced items during a rollback operation?
a.
Apply sequential version updates to each referenced item while maintaining prior relationships
b.
Implement a complete system-wide restoration of all artifacts to the specified historical point
c.
Roll back individual items based on the most recent timestamp of each artifact in the system
d.
Apply cascading version restoration to maintain referential integrity of linked artifacts
Expert