In a qualitative risk analysis of a smart city project, which formula best represents the calculation of the Risk Score (RS)?
a.
RS = P x I x V, where P is probability, I is impact, and V is vulnerability factor of urban infrastructure
b.
RS = P x I x M, where P is probability, I is impact, and M is mitigation effectiveness
c.
RS = (P + I) / 2, where P is probability and I is impact
d.
RS = P x I, where P is probability and I is impact