PMI-PBA - Risk Identification and Management - Risk Response Planning
Advanced
1/100
In a software development project, a risk has been identified that automated tests may produce unstable results. The team decides to run both automated and manual testing in parallel, requiring twice the effort. Which risk response strategy is being demonstrated?
a.
Acceptance with parallel testing methodology
b.
Risk transference to quality assurance team
c.
Enhancement through comprehensive test coverage and additional resource allocation
d.
Mitigation
Advanced