PMI-RMP - Communication and Risk Reporting - Risk Escalation Processes
Expert
1/12
What is the most effective way to implement a risk escalation threshold adjustment process during project execution?
a.
Review risk performance metrics and update thresholds based on actual project conditions
b.
Modify risk thresholds according to stakeholder feedback and their risk tolerance preferences exclusively
c.
Apply standard organizational risk thresholds and maintain them throughout the project lifecycle
d.
Establish escalation thresholds based on historical data from similar completed projects in the portfolio
Expert