PMI-RMP - Implementing Risk Responses - Risk Ownership and Assignment
Expert
1/10
What is the best practice for establishing risk ownership in a project with multiple contractors working across different time zones?
a.
Implement a shared responsibility model where all contractors collectively own and manage project risks through consensus
b.
Establish a rotating risk ownership schedule where each contractor takes turns managing project risks on a weekly basis
c.
Assign risk ownership based on the contractor with the most experience in handling similar risks from past projects
d.
Create a centralized risk ownership matrix with designated backup owners and clear handover protocols
Expert