1/21
When constructing an influence diagram for risk assessment, what is the primary purpose of using bidirectional feedback loops between value nodes?
a.
To show cascading effects of concurrent probability distributions across multiple value scenarios
b.
To represent mutual influence between interdependent outcomes
c.
To demonstrate the sequential progression of risk events through multiple decision points and their associated outcomes
d.
To indicate that both nodes must reach specific threshold values before activating subsequent processes