PMI-RMP - Risk Appetite and Tolerance - Definition and Role of Risk Tolerance
Expert
1/12
Which factor best defines how risk tolerance shapes a project's risk strategy?
a.
The measurable level of uncertainty an organization accepts for specific objectives
b.
The systematic evaluation of risk thresholds based on historical project performance data
c.
The maximum amount of risk exposure an organization can handle before project termination
d.
The comprehensive assessment of all potential risks and their impact on project deliverables over time