PMI-RMP - Risk Appetite and Tolerance - Measuring and Monitoring Risk Appetite Compliance
Expert
1/12
What is the most effective way to validate that a project's risk posture stays within risk appetite boundaries during execution?
a.
Weekly assessment of risk impact calculations and variance analysis from baseline expectations
b.
Monthly review of risk response effectiveness through stakeholder feedback mechanisms
c.
Comprehensive evaluation of all project risks through detailed qualitative analysis and expert judgment
d.
Regular monitoring of predefined risk metrics against established thresholds