PMI-RMP - Risk Attitudes and Biases - Optimism Bias in Risk Estimation
Intermediate
1/5
A Risk Breakdown Structure (RBS) for a project shows numerous risks with duplicate subcategories spread across all levels of the hierarchy. What key principle of RBS design is being violated?