PMI-RMP - Risk Categories and Taxonomy - Risk Breakdown Structure (RBS)
Expert
1/5
In a Risk Breakdown Structure (RBS), which method best represents the optimal way to handle risks that affect multiple project phases?
a.
Create a cross-phase risk category with sub-levels for each affected phase
b.
Duplicate the risk entry in each affected phase and maintain synchronized updates across all instances
c.
Place the risk in the phase where it has the highest potential impact and note secondary impacts
d.
Establish separate entries for each phase and create detailed cross-references between related risk entries
Expert