PMI-RMP - Risk Governance - Risk Communication and Reporting
Intermediate
1/5
While establishing a Risk Breakdown Structure (RBS) for a new project, what technique is most effective in maintaining a clear distinction between risk categories at each level?
a.
Creating flexible category boundaries that allow risks to be classified in multiple sections based on context
b.
Developing extensive subcategories with detailed descriptions and risk impact assessments for each category
c.
Using standardized naming conventions and clear category boundaries
d.
Implementing a comprehensive matrix system that maps all potential risk interactions across multiple organizational levels
Intermediate