PMI-RMP - Risk Thresholds and Triggers - Role of Risk Thresholds in Risk Prioritization and Ranking
Expert
1/5
How should changes in project scope impact the recalibration of established risk thresholds?
a.
Risk thresholds should be adjusted based on stakeholder emotions rather than scope changes
b.
Risk thresholds need complete recalculation whenever any minor change occurs in the project scope
c.
Risk thresholds should be adjusted in proportion to the extent of scope modifications
d.
Risk thresholds must remain constant throughout the project lifecycle to maintain baseline consistency