PMI-SP - Activity Definition and Sequencing - Critical Path Method (CPM)
Expert
1/5
In Critical Path Method (CPM), what defines the optimal crashing sequence when dealing with converging paths that share resources?
a.
The combined early start dates of all activities sharing the same resource pool on parallel paths
b.
The sequential compression of activities based on their resource allocation percentages and float values
c.
The total number of resources available multiplied by the expected completion duration of shared activities
d.
The ratio of cost increase to duration reduction for each parallel activity