When sequencing activities in a WBS, what constitutes a valid approach for managing nested dependencies?
a.
Establishing comprehensive dependency paths between all work packages across multiple hierarchical levels of the WBS structure
b.
Implementing parallel dependency paths that connect all activities regardless of their position in the WBS hierarchy
c.
Linking activities at the lowest level of decomposition where interdependencies exist
d.
Creating dependency relationships only between major deliverables at the highest level of the WBS to maintain project flexibility