PMI-SP - Activity Definition and Sequencing - Work Breakdown Structure (WBS)
Expert
1/5
When a project manager receives stakeholder input for WBS refinement during execution, what is the most appropriate response according to PMI-SP best practices?
a.
Update all project documentation and proceed with the suggested modifications to maintain stakeholder satisfaction
b.
Document the suggestions in the change log and continue with the current WBS until project completion
c.
Assess impact on control accounts before implementing approved changes
d.
Evaluate the changes against the baseline schedule and implement them in the next planning cycle