PMI-SP - Change Control and Schedule Updates - Impact Analysis of Schedule Changes
Expert
1/5
In schedule impact analysis, what is the most effective way to assess interdependencies between schedule changes and project resource allocation?
a.
Analyze critical path deviations and document resource utilization patterns in parallel activities
b.
Compare baseline resource curves against modified schedule scenarios
c.
Review project milestones and create detailed resource histograms for all schedule variations
d.
Calculate total float variations in the project management software for each resource pool