PMI-SP - Change Control and Schedule Updates - Integrated Change Control Process in Scheduling
Expert
1/5
When implementing Integrated Change Control in a schedule-intensive project, what is the primary focus of schedule baseline revisions?
a.
Analyzing historical performance metrics to predict future schedule performance trends and variations
b.
Updating the Work Breakdown Structure to reflect new activity durations and resource assignments
c.
Conducting detailed reviews of all schedule activities to maintain sequential progression of tasks and resource allocation
d.
Evaluating the cumulative impact of changes on project milestones and dependencies