PMI-SP - Change Control and Schedule Updates - Schedule Monitoring and Control Processes
Expert
1/12
In schedule monitoring and control, which approach should be used when a project's schedule variance is consistently negative over three reporting periods?
a.
Monitor the schedule metrics for two more reporting periods before implementing any corrective actions
b.
Update the schedule baseline and recalculate the critical path based on current performance metrics
c.
Apply fast tracking on critical path activities and request additional resources
d.
Analyze resource allocation patterns and adjust the critical path activities based on resource leveling techniques