11:59
Stop
PMI-SP - Communication Planning - Communication Constraints and Assumptions
Intermediate
1/12
During activity duration estimation for a major event management project, your team has access to three estimates for each activity: an optimistic estimate of 2 days, a most likely estimate of 4 days, and a pessimistic estimate of 12 days. Which value represents the expected duration using PERT?
Intermediate