PMI-SP - Critical Path Method (CPM) - Dependency Determination and Types in CPM
Expert
1/12
In CPM dependency analysis, what characterizes a preferential logic relationship between activities?
a.
A relationship mandated by contractual obligations and regulatory requirements
b.
A sequence established by organizational policies and standard operating procedures
c.
A sequence determined by physical limitations and fundamental project constraints
d.
A sequence based on best practices and past project experience
Expert