PMI-SP - Critical Path Method (CPM) - Schedule Compression Techniques: Crashing and Fast-Tracking
Expert
1/5
In Resource-Constrained Scheduling (RCS), when reallocating resources among parallel projects, what approach yields the most efficient resource utilization?
a.
Apply resource smoothing techniques across all projects based on deadline proximity
b.
Prioritize activities based on total float and project strategic value
c.
Allocate resources based on earliest start dates and activity duration estimates
d.
Distribute resources evenly across all projects while maintaining critical path sequences
Expert