PMI-SP - Critical Path Method (CPM) - Schedule Network Diagram Construction
Expert
1/12
When determining lag relationships in a Schedule Network Diagram, what is the most appropriate method for representing multiple concurrent dependencies with varying durations?
a.
Use CPM (Critical Path Method) to establish fixed lag values based on the longest dependency duration
b.
Apply PDM (Precedence Diagramming Method) with custom lag values for each relationship
c.
Implement a combined PDM-ADM hybrid system with standardized lag durations across all relationships
d.
Apply ADM (Arrow Diagramming Method) and calculate the weighted average of all dependency relationships
Expert