PMI-SP - Defining Schedule Objectives - Defining Milestones and Deliverables
Beginner
1/5
In a project schedule, what should a deliverable milestone primarily represent?
a.
A mandatory checkpoint where all team members must provide detailed status reports
b.
A key date when stakeholders review and approve all completed project activities
c.
A significant point where a specific measurable output has been achieved
d.
Any point in the schedule where multiple activities converge to produce an outcome