PMI-SP - Defining Schedule Objectives - Developing a Work Breakdown Structure (WBS)
Expert
1/12
What is the key consideration when assigning numbering codes to WBS elements?
a.
The codes should reflect the hierarchical structure and level of each component
b.
The codes must incorporate resource allocation percentages and cost estimates for each element
c.
The codes should be assigned based on the chronological order of project activities and their dependencies
d.
The codes should represent the priority level and risk assessment scores of each deliverable