PMI-SP - Defining Schedule Objectives - Establishing Schedule Baselines
Expert
1/12
When revising a schedule baseline, what is the most appropriate method for incorporating rolling wave planning adjustments?
a.
Update all future activities with detailed estimates based on current project performance metrics and stakeholder expectations
b.
Revise all baseline activities to reflect the most recent performance data and resource availability constraints
c.
Maintain original baseline estimates and add new detailed activities as separate schedule components for tracking purposes
d.
Update detailed activities for near-term work and maintain summary tasks for future work phases
Expert